STANDARE CONTRACT
APPENDIX-C
SCHENGULE OF QUANTITIES, PRICING AND PAYMNET CONDRRIONS
1.0 WORK TO BE PERFORMED
Except as specified elwhere in the Contract, except for the Employer supplied
material and equipment as detailed in the Scope of Work, Contractor shall supply
all the materials, labor, technical support, supervision, tools, equipment and plant,
transportation, consumable and perform all the works required for completion of
decoration work of Continent supermarket Fuangzhuang Fengtai district, Beijing
for employer. The construction area of the work is M more or less.
2
2.0 LUMP SUM PRICE
The Total Lump Sum Price for performing all work is temporarily
RMB 3,000,000.00Yuan, Say: RMB three million YUAN only (It is depend on
the actual work performed by the contractor under the mutual agreement)
Price Notes
The lump Sum Price includes, but not limited to, the cost of works, taxes
and charges, overhead and profit and all the expens which could be
required by Contractor for the completion of the Works under the Contract.
Unless there will be change in the Scope of Wok shown by the current
drawings, no variation daim will be entertained.
3.0 UNIT PRICES FOR CHANGES
Unit prices for changes shall be full and complete compensation for additional
work or credit for deleted work. Prices include but not limited to, labor, material,
rvices, overhead and profit. The Unit Prices shown in the bid package
submitted earlier will be ud as a reference basis in evaluating future variations.
Tho items of variation which do not have reference basis shall be priced in
accordance with quota.
4.0 ADJUSTMENTS
All prices are fixed for the duration of the Contract and are not subject to
escalation for any cau. Payment of the Total Contract Price shall constitute full
payment for performance of the Work and covers all costs of whatever nature
incurred by Contractor in accomplishing the Work in accordance with the
provisions of the Contract.
5.0 REOUIRED SUBMITTALS
The following submittals are a prerequisite to the initial payment after the award
of contract;
5.1 Contract Schedule
5.2 Execution Plan
6.0 TERMS AND CONDITIONS OF PAYMENT
6.1 The total sum value is temporarily RMB3,000,000.00.(Say: three million
RMB yuan only), Contract singed after and satisfying the conditions of
down payment; Pay 30% of contract sum (RMB9000,000.00Yuan, Say:
nine hundred thousand RMB Yuan for preparation fee);
6.2 40% finished :Pay 30% of contract sum (RMB600,000.00 Yuan, Say: nine
hundred thousand RMB Yuan);
6.3 80% finished: Pay 20% of contract sum ( RMB6000,000.00 Yuan, Say: six
hundred thousand RMBYuan);
6.4 after final checking by employer, government,. The actual construction cost
will be checked and confirmed by party A, party B, and supervisory
company. The rest 15% to be paid after final checking. The principle as
following;
6.4.1 According to Beijing 96 Budget Price Book.
6.4.2 Becau it is night work, so the civil engineering labor fee is
RMB40.00/day, the installation labor fee is RMB30.00/day. And the night
work cut down efficiency fee can not be charged.
6.5 Maintenance fee 5%of contract sum will be paid after one year of
maintenance. For the progress payment, the Contractor shall submit to
Employer his written request supported by a statement of accomplishment
for review, then the Site Manager assigned by the Employer shall review
the payment request. The Site Manager shall endor payment request after
review to Employer for relea of payment. The whole process from the
submission of the written request to the relea of payment shall be within
two weeks.
STANDARD CONTRACT
APPENDIXD-1 WORK SCOPE
This appendix D-1(hereinafter referred to as work scope)is made on the day of 1
June 2000
1. General rules
Fangzhuang store modification and reconstruction should be performed strictly in
accordance with demand of owner, the drawing, technical specification, some
concerned rules and the provisions stipulated in the contract, the work performed
should meet the following national standard《Architectural Installment Quality
Checking Evaluation Unified Standard》(GBJ300-80)
Except the equipment supplied by the Employer and the equipment installed and
tested by the special contractor assigned by the Employer, all the work scope
implement must be carried on according to concerned rules of testing, adjustment
and operation.
2. Work scope
2.1 Construction modification (including main entrance and exit modification)
2.2 Electric system modification (including fresh area lighting fitting)(the lamp
supplied by party A)
2.3 HVAC system modification (including fresh area system and new fan)
2.4 W/S & drainage system modification
3. work out of scope
3.1 weak electric system install;
3.2 Fire-fighting system equipment and install;
3.3 Electric、W/S &drainage equipment install;
3.4 Distribution room main switch;
Appendix D-1
本文发布于:2023-11-04 06:52:21,感谢您对本站的认可!
本文链接:https://www.wtabcd.cn/zhishi/a/1699051941205773.html
版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。
本文word下载地址:STANDARD CONTRACT( 标准合同).doc
本文 PDF 下载地址:STANDARD CONTRACT( 标准合同).pdf
留言与评论(共有 0 条评论) |