说明

更新时间:2023-05-09 20:06:49 阅读: 评论:0

1. Table 1. List of Vendor Prints Required為工程公司Toyo規定必須依照時程提出之文件,具有強制性。
2. Toyo基準ED-000-PJM-PRC-000822頁到第24頁列出客戶需準備待審文件,為非強制性,然業主/Toyo提出審核要求,便需提供;其內容及各單位分配請詳下列內容(若覺得分配有需討論之處,煩請提出,謝謝)
ED-000-PJM-PRC-0008
Attachment-1 -1/3
Vendor Document Handling Procedure
Attachment -1 Vendor Document To Be Submitted
Vendor shall prepare and submit document listed below but not limited. Specific document submission requirement will be described in each Material Requisition documents.
(1) Project Management Documents such as:
Vendor Print Index and Schedule (VPIS)各單位
Vendor’s Organization Chart營業
Sub-Vendor list and Suborder Sheet營業
Sub-Order Status Report
Manufacturing Schedule (with two weeks from receipt of Purcha Order or Letter of Intent)  生管
Monthly Status Report生管
Declaration of Receipt of Major Raw Material→QA
Inspection and test Schedule→QA
(2) Technical Documents such as :
Technical Specification→Toyo
Equipment Date Sheet→Toyo
Performance Curve→Toyo
Strength Calculation設計
Process and Utility Flow Diagram→Toyo
Piping and Instrument Flow Diagram (P&ID) →Toyo
Utility and Chemical Consumption Data→Toyo
Effluent Summary→Toyo
General Asmbly Drawings設計
Detail Asmbly Drawings設計
Layout Drawing→Toyo
Piping Drawings including Isometric drawings→Toyo
Electrical Load List→Toyo
Equipment Loading Data for Civil Design→Toyo
Instrument Schedule→Toyo
Logic Diagrams→Toyo
Wiring drawings for instrumentation→Toyo
Wiring drawing for Electrical System→Toyo
Wiring drawing for Tele-Communication System→Toyo
Welding Procedure生技
Painting Schedule工務
(3) QA/QC Document / Manual
QA/QC Manual→QA
ED-000-PJM-PRC-0008
Attachment-1 -2/3
Vendor Document Handling Procedure
Attachment -1 Vendor Document To Be Submitted
Quality Assurance Plan→QA
Fabrication Procedures生管
Inspection and Test Plan→QA
Material Handling, Storage Protection and Prervation Requirement工務
  Notes:
  Vendor shall submit the procedures for the handling, cleaning, storage, shipping, prervation and    preventative
maintenance of materials and equipment from the time of arrival at the WORK site until mechanical completion.
This procedure shall include requirements for the u and application of Rust Preventives.
Any special handling, prervation, storage, cleaning, packaging and shipping requirements will be identified, particularly tho that must be accomplished by qualified individuals in accordance with predetermined WORK and inspection instructions.
Installation Manual
Pre-Commissioning and Commissioning Procedure
Operation Manual
Maintenance Manual
(4) Shipping and Packing Documents生管
Estimated Cargo Volume with Remark Point
Equipment and Material List for Packing
Preliminary Packing List
Detail Packing List
Packing Tagging Indication
Packing and Un-packing Manual
(5) Spare Parts and Special tool documents生管
  Erection and Commissioning Spare Parts List
  2 Years Operation Spare Parts List
  Inter-changeable Spare Parts List
  Grea and Lubricant List
  Special Tools list
(6) Manufacturing Date RecordQA
Material Test Certificates.
Stage & Final Inspection Certificates
Heat Treatment Charts
Radiographic Examination Results
Inspection Report on Mechanical and Performance Test Runs, including Performance Curves, Power Consumption, etc.
Rubbings of any Third Party Inspection Authority Stamps
Equipment Nameplates
ED-000-PJM-PRC-0008
Attachment-1 -3/3
Vendor Document Handling Procedure
Attachment -1 Vendor Document To Be Submitted
Certificates of acceptance of compliance with code設計

本文发布于:2023-05-09 20:06:49,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/90/102376.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:文件   提出   分配   內容   制性   單位   需準
相关文章
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图