PCB专业英语词汇

更新时间:2023-05-09 04:17:35 阅读: 评论:0

PCB专业英语词汇
一. Process 工艺流程
1. Board cut /开料
2. Drill /钻孔
3. IQC(Incoming Quality Control) /来料检查
4. PTH(Plated Through Hole) /沉铜
5. Panel Plating /整板电镀
6. D/F(Dry Film) /干膜
7. Pattern Plating /图形电镀
8. ETCH /蚀刻
9. QC (Quality Control) /品质检查
10. W/F(Wet Film) /湿膜
11. Legend /字符
12. HAL(Hot Air Leveling) /喷锡
13. Immersion gold (chemical gold) /沉金
14. Routing /
15. V-CUT /V
16. Punting /
17. Rin /清洗
18. FQC(Final Quality Control) /终检
19. QA  Audit /审核
20. Package /包装
21. Shipment /出货  ship out
二. The items For QA
1. PQC(Process Quality Control) /过程品质检查
2. IPQC(In Process Quality Control) /过程控制检查
3. First Article check /首件检查
4. Backlight /背光检查
5. Microction /切片检查
6. Etch Factor /蚀刻系数
7. Tape test /胶纸实验
8. Lot check /批检
9. Full check /全检
10. Sampling check /抽检
11. Customer /客户
12. Date code /日期代码
13. AQL level(Average Quality Level) /AQL水平
14. Sample size /抽样数
15. Lot size /批量数
16. Visual check /目视检查
17. Logo /商标
18. Solder side /焊接面
19. Component side /元件面
20. Gold tape test /金层结合力实验
21. S/M tape test /绿油结合实验
22. C/M tape test /字符结合实验
23. Impedance test /阻抗测试
24. Wetting test(solder ability test) /可焊性实验
25. Specimen 样板,样品
26. Outgoing Report(shipment report) 出货报告
27. ACC(Accepted) 可接受
28. Rej (Rejected) 拒收
29. Pass
30. UAI(U As Is) 特采 (让步接受)
31. Defect 缺陷
32. Corrective Actions 纠正措施
33. MRB(Material Review Bcard) 物料审核委员会
34. Customer Complain 客户投诉
35. DCC(Document Control Center) 文控中心
三. The items for Engineering Department
1. Engineering Department工程部
2. QE: Quality Engineering 品质工程师
3. MI: Manufacturing Instruction生产指引
4. ECN: Engineering Change notice 工程变更通知
5. Template 模板
6. E/T Fixture测试架
7. Ground Layer地层
8. Inner Layer内层
9. Dummy Pad(inner layer)PAD
10. Artwork Check
11. Pattern
12. Pattern Artwork
13. S/M Artwork
14. Legend Artwork字符非林
15. Carbon Artwork
16. CAD: Computer Assistant Design
17. CAM: Computer Assistant Manufacturing
18. MI Audit
19. Tolerance
20. Second Drill
21. Tenting
22. certificate / 证书
23. clear / 清除
24. client / 客户
25. samples 样板/样品
四. Year or week and month
1. week:星期
2. Monday1:星期
3. Tuesday
4. Wednesday
5. Thursday
6. Friday
7. Saturday
8. Sunday/first day
9. month:
10. January 1
11. February 2
12. March 3
13. April 4
14. May 5
15. June 6
16. July 7
17. August 8
18. September 9
19. October 10
20. November 11
21. December 12
Other one glossary
1. Guarantee  保证
2. Calibration  刻度
3. hole 孔,洞

本文发布于:2023-05-09 04:17:35,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/90/101527.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:实验   检查   电镀   品质   结合   过程
相关文章
留言与评论(共有 0 条评论)
   
验证码:
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图