Construction Schedule Control Procedure
施工进度控制流程
Purpo: define and standardize project construction schedule control procedure and requirement
目的:明确项目施工进度控制流程与要求并使其标准化。
Direction: construction engineer and scheduler will employ the procedures and guideline detailed within this document to provide a consistent approach to the scheduling effort at jobsites.
用途:项目工程师与计划员将采用本流程,以及本文中提及的详细步骤,对现场的计划工作进行标准化控制。
SCHEDULING FLOWCHARTS
进度流程图
Construction Schedule Control Flow Chart
8
Conduct submits prelim schedule to ABI on CPM向百威提交网络图形式的初步计划
施工进度控制流程图
好书分享ppt4
Conduct post-bid meeting. Review milestone of BP 召开澄清会。审查标段结点是否满足
2
Contractor pre-bid meeting承包商标前会
1
Develop BP milestone提供标段结点
3
Contractor’s bid includes level 3 schedule承包商标书中包括三级工期计划
12
Contractor to incorporate  adjustment 承包商根据反馈修改其计划
感恩节是哪一天7
Contractor develops level 4 schedule with/ Act/ Dur/ MHs 承包商提供四级计划,包括工序/工期/人工时
6
龙猫的图片Contractor receives contract and schedule submittals承包商收到合同与所需提交的计划清单及表格
降脂灵片
5
ABI to prepare schedule submittals which contractor need submit百威准备承包商需要提交各种计划的标准表格
红果果个人资料11
ABI to coordinates all contractor’s schedule and returns adjustment to contractor百威合并所有承包商的计划并反馈给承包商需进行调整的部分
9
Is preliminary schedule acceptable to ABI拨云撩雨百威是否认可初级计划?
10
茭头炒腊肉ABI to merge contractor’s schedule into master project schedule百威将承包商的计划并入项目总计划
    Yes认可
                                                                                            No不认可
14
Is schedule acceptable to ABI百威是否认可计划?
                                                                No不认可
13
Contractor  to submit contractor’s schedule to AB on  CPM承包商向百威提交关键线路网络图计划
15
ABI to merge contractor’s schedule into master schedule百威将承包商的计划并入总计划
                                                                                                                                                                          Yes认可
18
contractor to submit billing report according their progress monthly承包商每月根据实际进度提交进度款报告
17
contractor maintains “current” schedule updates承包商跟踪并更新“当前”计划
16
ABI and contractor t up “current” schedule百威与承包商共建“当前”计划
15
ABI to merge contractor’s schedule into master schedule百威将承包商的计划并入总计划
                                                                                                       
                                                                                                        Weekly cycle周循环                                    Monthly cycle月循环
20
ABI to analyze reports and update master schedule 百威分析报告并更新总计划
21
ABI replaces master schedule files on website百威在网上更新总计划
19
contractor to submit weekly  reports and 3week look ahead schedule 承包商提交周报告与三周向前看计划
22怎么做鸡
ABI approves and forwards cost summary report for billing 百威批准并将工程进度款报告发给财务付款

本文发布于:2023-05-22 02:40:53,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/89/922832.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:计划   承包商   百威
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图