5 | 设备安装 equipment installation ps自动拼图 | |||||||||
5.1 | 容器与换热器安装vesls and heat-exchangers installation | |||||||||
5.1.1 | 进场检验 Receiving inspection | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J115 |
5.1.2 | 基础检查交接 Foundation handover | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | A | I | H | H | -- | J204 | |
5.1.3 | 基础准备 Inspection of Foundation preparation | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | B | I | W | W | -- | -- | J204 |
5.1.4 | 开工报告 Commencement Report | 合同要求 Contract specification | 开工前 Before commencement | A | H | H | H | H | -- | SH/T3503-J105A |
5.1.5 | 向特检院报检 BPVI Notice(pressure vesl) | BPVI Requirement | 开始前 Before commencement | A | H | R | R | -- | H | BPVI Format |
5.1.6 | 检查安装调整(位置、标高、水平方位、垂直度,方向) Check alignment(position, height, level, verticality, orientation) | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | B | I | W | W | -- | -- | J314,J315 |
5.1.7 | 底板灌浆 Grouting ba plate | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | B | I | W | W | -- | -- | J111,J130 SH/T3543 G116 |
5.1.8 | 梯子、平台安装 Ladder, platforms asmble | GB50205 SH/T3532-2005 | 按要求 As required | B | I | W | W | -- | -- | 自检记录lf-checking record SH3514-P1302 |
5.1.9 | 向特检院报检 BPVI Acceptance for pressure vesl | BPVI Requirement | 按要求 as required | A | I/R | R | -- | -- | H | BPVI Format |
5. 1.10 | 封闭前内部检查 Inspection of Internal Equipment | SH/T3542-2007 SH/T3532-2005 | 按需要 As required | B | I | W | W | H | -- | F7407 |
乌雕 5.1.11 | 最终外观检查(尾项清单) Final visual inspection (punch list) | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | A | I | H | H | H | -- | Extra129 |
5.1.12 | 机械验收 Mechanical Acceptance | SH/T3542-2007 SH/T3532-2005 | 每台设备 Each equipment | A | I | H | H | H | -- | F02451 |
5.2 | 塔、冷却塔安装 Installation of column, Cooling Tower | |||||||||
5.2.1 | 进场检验 Receiving inspection | SH/T3542 SH/T3514-2001 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J115 |
5.2.2 | 基础检查交接 Foundation handover | SH3542 SH/T3514-2001 | 每台设备 Each equipment | A | I | H | H | H | -- | J204 |
5.2.3 | 基础准备 Inspection of Foundation preparation | GB50231-98 SH/T3532-2005 | 每台设备 Each equipment | B | I | W | W | -- | -- | J204 |
5.2.4 | 向特检院报检 BPVI Notice(pressure vesl) | BPVI Requirement | 开始前 Before commencement | A | H | R | R | -- | H | BPVI Format |
5.2.5 | 塔预吊装检查 Check pre-asmbling | SH3515/3542 SH/T3514-2001 | 每台设备 Each equipment | B | I | W | W | -- | -- | 自检记录lf-checking record |
5.2.6 | 检查安装调整(位置、标高、垂直度、方位) Check alignment (position, height, verticality, orientation) | SH3542 SH/T3514-2001 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J314 |
5.2.7 | 底板灌浆 Grouting ba plate 自我反思100字 | SH3542 SH/T3514-2001 | 每台设备 Each equipment | B | I | W | W/R | -- | -- | J111,J130 |
5.2.8 | 梯子、平台安装 Ladder, platforms asmble | GB50205 SH/T3514-2001 | 按要求 as required | B | I | W | S | -- | -- | 自检记录lf-checking record 3514-P1302 |
5.2.9 | 封闭前内部检查 Internal Inspection of equipment before closing | SH/T3542 | 按需要as required | B | I | W | W/R | -H- | F7407 | |
5.2.10 | 向特检院报检 BPVI Acceptance for pressure vesl | BPVI Requirement | 按要求 as required | A | I/R | R | -- | H | BPVI Format | |
5.2.11 | 最终外观检查(尾项清单) Final visual inspection (punch list) | GB50231-98 SH/T3514-2001 | 每台设备 Each equipment | A | I | H | H | -H- | Extra129 | |
5.2.12 | 机械验收 Mechanical Acceptance | GB50231-98 SH/T3514-2001 | 每台设备 Each equipment 聊斋志异之小谢 | A | I | H | H | H | -- | F0245 |
5.3 | 塔盘、内构件与填料安装 trays, internals and packing installation | |||||||||
5.3.1 | 进场检验 Receiving inspection | SH3542 SH/T3514-2001 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J115 |
5.3.2 | 支撑圈和梁安装 Support ring and beam installation | SH3542 SH/T3514-2001 | 按需要as required | B | I | W | S | W | 自检记录lf-checking record | |
5.3.3 | 检查塔盘装配(方位、螺栓、水平、堰高等) Check tray asmbling orientation bolting, level, weir height, baffles | SH3542 SH/T3514-2001 | 按需要as required | B | I | W | W/R | W | J316 | |
5.3.4 | 密封与强度 Check al and strength welding | SH3542 SH/T3514-2001 | 按需要as required | B | I | W | W | -- | -- | J329 |
5.3.5 | 人行通道封闭 Access clo | GB50231-98 SH/T3514-2001 SH3542 | 按需要as required | B | I | W | W | -- | -- | J111 |
debate的用法5.3.6 | 填料安装 Check filling packing | GB50231-98 SH/T3514-2001 SH3542 | 按需要as required | B | I | W | W | W | -- | J317 |
5.3.7 | 封闭前内部检查 Inspection of Internal Equipment | GB50231-98 SH/T3514-2001 SH3542 | 按需要as required | B | I | W | W/R | W | -- | F7407 |
5.3.8 | 最终外观检查(尾项清单) Final visual inspection (punch list) | GB50231-98 SH/T3514-2001 | 每台设备 Each equipment | A | I | H | H | H | -- | Extra129 J111 |
5.4 | 一般动设备安装rotating equipment installation(General) | |||||||||
5.4.1 | 进场检验 Receiving inspection | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J115 |
5.4.2 | 设备保管维护 Storage of Equipment | GB50231-98 SH3541 | 每台设备 Each equipment | B | I | W | S | -- | -- | 自检记录lf-checking record |
5.4.3 | 基础检查交接 Foundation work handover | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | B | I | H | H | H | -- | J204 3543-G112 |
5.4.4 | 基础准备 Inspection of Foundation preparation | downtown GB50231-98 SH/T3532-2005 SH3541 | 每台设备 Each equipment | B | I | W | W | -- | -- | SH/T3543 G113 J204 |
5.4.5 | 设备安装检查 Equipment Installation Inspection | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | B | I | W | W | -- | -- | J301 |
5.4.6 | 地脚螺栓一次灌浆 Initial grouting for anchor bolt | GB50231-98 GB50275-98 | 每台设备 Each equipment | B | I | W | W | 打印机状态错误是怎么回事-- | -- | J111 |
5.4.7 | 二次灌浆 cond grouting | GB50231-98 GB50275-98 | 每台设备 Each equipment | B | I | W | W | -- | -- | J111,J130 |
5.4.8 | 联轴器一次对中检查 1st Coupling final- alignment | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | B | I | W | W | -- | -- | J302 |
5.4.9 | 管道安装检查(无应力检查) Piping installation check ( no-stress check ) | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | B | I | W | W | -- | -- | SH3543-G402 Extra-418 |
5.4.10 | 联动器最终对中检查 Coupling Final-Alignment | GB50231-98 GB50275-98 | 每台设备 Each equipment | B | I | W | W | -W- | -- | J302 |
5.4.11 | 单机试运行 Single running test of Equip. | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | A | I | H | H | -H- | -- | J306 |
5.4.12 | 最终外观检查(尾项清单) Final visual inspection (punch list) | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | A | I | H | H | -H- | -- | Extra129 |
5.4.13 | 机械验收 Mechanical Acceptance | GB50231-98 GB50275-98 SH3541 | 每台设备 Each equipment | A | I | H | H | H | -- | F0245 |
5.5 | 现场储罐制作安装 site storage tank installation | |||||||||
5.5.1 | 进场检验 Receiving inspection | GB50128-2005 SH/T3530-2001 | 每台设备 Each equipment | B | I/QR | W/R | W/R | -- | -- | J131 |
5.5.2 | 基础检查交接 Foundation handover | GB50128-2005 SH/T3530-2001 | 每台设备 Each equipment | A | I | H | H | H | -- | J209 |
5.5.3 | 基础准备 Inspection of Foundation preparation | GB50128-2005 SH/T3530-2001 | 每台设备 Each equipment | B | I | W | W | -- | -- | J204 |
5.5.4 | 焊接工艺评定与焊接工艺指导书 WPS & PQR | GB50128-2005 SH/T3530-2001 | 开始前before commencement | A | H | H | R | R | -- | 审核记录review record |
5.5.5 | 焊工证书及考试 Welder certification and qualification test | GB50128-2005 SH/T3530-2001 | 每个焊工each welder | B | T/QR | W/R | W/R | -- | -- | 审核记录review record |
5.5.6 | 组对检查 Fit-up Inspection | GB50128-2005 SH/T3530-2001 | 每个口each joint | B | I | W | S | -- | -- | Extra412 |
5.5.7 | 焊接外观检查 Welding visual inspection | GB50128-2005 SH/T3530-2001 | 每个口each joint | B | I | W | S | -- | -- | Extea.412 |
5.5.8 | 渗透检查 NDT inspection (P.T) | JB/T4730.5-2005 | 按要求as required | B | T | H | W | R | -- | J127 |
5.5.9 毛细作用 | 磁粉检查 MT | JB/T4730.4-2005 | 按比例as scale | B | T | H | W | R | -- | J126 |