序号 No | 批准名称 Name of Permit | 授权人(法) Grantor (Law) | 申报文件 Documents Required | 审查/检查时间 Time of approval and examination | 部门名称大全
1 | 施工规划许可证报审 Review of construction Planning Permit | 规划局 Planning Bureau | 1.申请表Application Form 2.土地使用证Land U Permit 3.地形图、平、立剖等 Land map, Plane and Section Drawing | 施工开始前 Before Construction |
2 | 施工许可证报审 Construction permit | 市建委 Municipal Construction Bureau | 1.申请表Application Form 2.施工安全和质量监督委托书 Letter of Safety and Quality Inspection Delegation 3.施工合同Construction contract 4.承包商在当地建委的注册通知 Letter of Registration in Local Construction Bureau | 施工开始前 Before Construction |
3 | 施工安全监督管理委托 Construction Safety Supervision Delegation | 国家或当地安全监 督检查代理机构 State or local safety supervision agency | 1.申请表Application Form 2.施工合同Construction Contract 3.承包商和分包商资质证明 Contractor and Subcontractor Qualification Certificate 4.安全手册及文件Safety Manual & Documents 5.安全组织机构图 Organization Chart for Safety Management | 施工开始前 Before Construction |
4 | 施工质量监督管理委托 Construction Quality Supervision Delegation | 国家或当地质量监督检查代理机构 State or local Quality supervision agency | 1.申请表Application Form 2.施工合同Construction Contract 3.承包商和分包商资质证明 Contractor and Subcontractor Qualification Certificate 4.技术文件审批报告 Report on Technical Document Review | 施工开始前 三鲜虾仁馄饨Before Construction |
5 | 消防系统安装许可 Permit of Installation of Fire Protection System | 消防局 Fire Protection Bureau | 1.申请表Application Form 2.设计图纸Design Drawing | 安装前 Before Installation |
6 | 临时居民注册 Registration for Temporary Residents | 公安局 Public Security Branch | 1.身份证复印件Copy of Personal Identity Card 2.人员登记表Personnel Registration Form 3.通过计生办的流动人口结婚证明 Floating Person Marriage Certificate Through Family Planning Office | 施工开始前 Before Construction |
7 | 压力管道安装许可 Installation Permit of Pressure Pipe | 技术质量监督局 Quality Technical Supervision Bureau | 1.申请表Application Form 2.安装计划和设计图纸 Installation Planning and Design Drawing 3.相关图纸的报审批复 Approval for Relevant Drawing’ Review | 压力管道安装前 Before Installation of Pressure Pipe |
8 | 紧急的反义词特种作业的审批 Approval of special operations | 技术质量监督局 Quality Technical Supervision Bureau | 1.施工许可证申请表 Application Form for Construction Permit 2.施工/安装方案 Construction and Installation Procedure 3.相关图纸和文件 Relevant Drawings and Documents | 施工开始前 Before Construction |
9 | 施工质量检查 Construction Quality Inspection | 质检站 Quality Inspection Agency | 1.施工工序检查程序 Construction Sequence Procedure 2.报验申请表 Record of Construction Application Form 3.施工记录Record of Construction | 施工过程中 During Construction |
10 | 消防设施安装检查 Firefighting Facility Installation Inspection | 消防局 Firefighting Bureau | 1.材料质量检查报告 Material Quality Inspection Reports 2.施工记录 Records of Construction | 施工过程中 During Construction |
11 | 环保设施安装检查 Environmental Protection Facility Installation Inspection | 环保局 Environmental Protection Bureau | 1.材料质量检查报告 Material Quality Inspection Reports 2.施工记录Records of Construction | 施工过程中 During Construction |
12 | 安全设施施工检查 Safety Facility Installation Inspection | 人生是一场旅行安全监督局 Safety Supervision Bureau | 1.材料质量检查报告 Material Quality Inspection Reports 课题成果2.施工记录Records of Construction | 施工过程中 During Construction |
13 | 特种设备安装检查 Special Equipment Installation Inspection | 技术质量监督局 Quality Technical Supervision Bureau | 1.安装许可申请表 Application Form for Installation Permit 2.施工安装计划、图纸和其他相关资料 Construction Installation Plan,Drawing and Other Relevant Documents 3.安装实体的安全证明 Safety Certificate of Installation Entity 4.相关人员的资格证明 Qualification Certificate for Relevant Personal | 施工过程中 During Construction |
14 | 质量验收 Quality Acceptance | 技术质量监督局 Quality Technical Supervision Bureau | 1.竣工图纸Construction Completion Drawing 2.交工文件Documents for Plant Handover 3.验收测试文件Acceptance and Testing Documents | 施工完成之后 After Construction Finished |
15 | 消防系统现场测试和验收 Test and Acceptance for Fire Protection System In Site | 消防局 Fire Protection Bureau | 1.设备信息Equipment Information 2.制造商的生产许可 Production Permit of The Manufactures 3.设备验收测试报告 Testing Report of Equipment Acceptance 4.竣工图纸Construction Completion Drawing | 施工完成之后 系统开车之前 After Construction Finished Before Start-up |
16 | 测试仪表的合法检定 Measure Instrument Legal Calibration | 技术质量监督局 Quality Technical Supervision Bureau | 1.测试仪表的数据表The Data of Measure Instrument 2.委托文件Delegation Documents 3.资格证明Qualification Certification | 系统开车之前 Before Start-up |
键盘没反应是怎么回事17 | 环保设施验收 Acceptance of Environmental Protection Facilities | 环保局 Environmental Protection Bureau | 1.竣工图纸Construction Completion Drawing 2.交工文件Documents for Plant Handover 3.验收测试文件Acceptance and Testing Documents | 使用前 Before Usage |
18 | 防雷设施检查和验收 Inspection & Acceptance of Lightning Protection | 防雷检测所 Lightning Inspection Bureau | 1.竣工图纸Construction Completion Drawing 2.交工文件Documents for Plant Handover 3.验收测试文件Acceptance and Testing Documents | 使用前 Before Usage |