Forth Replacement Crossing – Scotland, UK

更新时间:2023-07-06 19:33:02 阅读: 评论:0

Available online at vailable online at Procedia Engineering          Procedia Engineering  00 (2011) 000–000 /locate/procedia The Twelfth East Asia-Pacific Conference on Structural Engineering and Construction
Forth Replacement Crossing – Scotland, UK
S. KITE 1, N. HUSSAIN 2, and M. CARTER 3
1
靶心率的计算公式Associate Director, Arup, London, UK (steve.) 2Director and Arup Fellow, Arup, Hong Kong (naeem.)
3 Associate Director, Arup, Hong Kong (matt.) Abstract
The Forth Replacement Crossing will be built across the Firth of Forth in Scotland to maintain and enhance a vital transport link.  The wide estuary will be crosd by a cable stayed bridge with 3 towers and a pair of 650 m main spans.  In the centre of each main span the stay cables will overlap to stabili the central tower, a unique design feature for a bridge of this scale.
The scheme design of the crossing has been carried out by the Jacobs Arup joint venture in accordance with the Eurocodes and project specific design criteria.  The structure will provide a fitting 21st century icon, to stand alongside the existing cantilever rail bridge from the 19th century and road suspension bridge from the 20th century, both Grade A listed bridges.
Keywords : cable-stayed bridge; Eurocode; wind tunnel testing.
1.INTRODUCTION
The Firth of Forth is a dramatic estuary which parates the Scottish capital of Edinburgh from the河套平原
Kingdom of Fife to the north.  The downstream crossings of the Forth at Queensferry are a pair of historic bridges - the iconic cantilever rail bridge constructed in the 1880’s (Mackay 1993) and the Forth Road Bridge (Anderson et al 1965), Britain’s first long span suspension bridge, which was opened in 1964.
Despite significant investment and maintenance over its lifetime, the Forth Road Bridge is showing
signs of deterioration as a result of incread traffic and the influence of weather.  In 2005, investigations of the main cables (Colford 2008) revealed rious corrosion, which if left unchecked c
ould lead to the bridge being clod to heavy goods vehicles as early as 2014, and to all traffic by 2019.  A comprehensive study into the future transport needs concluded that a replacement crossing is required.
The replacement bridge will be slightly to the west of the existing bridges, making u of a natural
granite outcrop in the middle of the Forth to allow the wide estuary and two navigation channels to be 1877–7058 © 2011 Published by Elvier Ltd.
doi:10.1016/j.proeng.2011.07.186
Procedia Engineering 14 (2011) 1480–1484
S. KITE et al. / Procedia Engineering 14 (2011) 1480–14841481 2Author name / Procedia Engineering 00 (2011) 000–000
crosd by a cable stayed bridge with a pair of 650 m main spans, with an approach viaduct to the south.  Selection of the scheme with the minimum impact on the environmentally constrained area and the reasoning behind the overall structural layout are described in Carter et al 2009.
Figure 1: Visualisation: Three centuries of engineering in the Firth of Forth
2.PROCUREMENT
The client, Transport Scotland, is procuring the crossing through a Design and Build contract.  This
will bring experience from contractors into the project at a suitable stage and allow the chon contractor克什米尔问题
to tune the design to suit his preferred methods of working and maximi efficiency.  The dialogue period
with tenderers is being run in parallel with the parliamentary process which will lead to an Act enabling powers for construction.
乌龟的种类Tenders will be submitted in January 2011, with contract award and start of construction anticipated
for April 2011, aiming for completion of the bridge in 2016.
3. THE SPECIMEN DESIGN
The Specimen Design of the crossing is a scheme design incorporating a high level of detail which has been produced by the Jacobs Arup joint venture.  Transport Scotland wanted to have this specimen design
for veral purpos: in order to verify the feasibility of the bridge arrangement, to define the overall form
and geometry of the crossing, to inform the environmental asssment and the Bill of Parliament, to enable a detailed cost build up to be calculated, and to be an illustrative design as a starting point for the tendering contractors from which to prepare their design proposals.
The total length of the bridge is 2,638 m.  Although the crossing is divided into a cable stayed bridge
and a southern approach viaduct, the structure is continuous from abutment to abutment with no inte
rmediate expansion joints.  Longitudinal fixity is provided by a monolithic connection at the Central Tower located on Beamer Rock with transver support provided at all towers and piers.
The towers are vertical reinforced concrete elements located in the centre of the deck with two planes
of stay cables anchored centrally in the “shadow” of the tower between the carriageways.  The stay cables overlap in the centre of the main spans.  The deck itlf is a streamlined box girder and stay cables are multi-strand type.
The key design requirements for the approach viaduct are long spans to minimi environmental impact, and visual continuity with the cable stayed bridge.  One span in particular must cross the Port Edgar Barracks and adjacent road in a single span of 90 m.  The aesthetic requirements are achieved by a
1482S. KITE et al. / Procedia Engineering 14 (2011) 1480–1484
Author name / Procedia Engineering 00 (2011) 000–000 3 pair of constant depth box girders supported on V-shaped piers. The transver paration of the
carriageways is constant, and this also suits the road geometry to either side of the main crossing.
Figure 2: General Arrangement
During preparation of the Specimen Design it became clear that there was no clear advantage to distinguish between all-steel orthotropic and steel-concrete composite construction for the cable stayed
bridge deck box. Therefore both options have been worked up as design solutions, and the contract
permits either to be adopted.  The heavier composite deck variant has stay cables spaced at typically 16.2
m whereas for the orthotropic variant a typical spacing of 25 m is adopted.
Similarly for the approach viaduct deck the choice between composite and prestresd concrete construction for the twin boxes was not driven by significant cost difference, so designs for both variants
were completed and the option left open.  Incremental launching is assumed for the composite option, and紫团山
in-situ balanced cantilevering for the prestresd concrete.
Composite Orthotropic
Concrete Composite
有关春节的传说
Figure 3: Deck ctions, showing all variants
S. KITE et al. / Procedia Engineering 14 (2011) 1480–14841483 4Author name / Procedia Engineering 00 (2011) 000–000
4.DESIGN PROCESS
4.1.Basis of Design
The Forth Replacement Crossing is one of the first major bridges in the UK to be designed to the Eurocode, implemented in April 2010.  Work on the Specimen Design commenced in early 2008 when
not all of the UK National Annexes and other implementation documents were available. The design criteria to be ud for the structural design are t out in a project specific Design Basis document which
has been updated and simplified as more national documents have been published. The final version forms part of the contract, providing additional rules and criteria appropriate to the bridge as well as clarifying how some of the Eurocode rules should be interpreted.  Aspects such as the site specific wind climate and the rules for ship impact criteria have been defined.
4.2. Analysis
The overall structural analysis was carried out using 3D global computer models.  Additional local and mi-local analysis models were established to examine more cloly the distribution of stress and to
aid in calibration of the behaviour of the global models.
4.3. Wind Tunnel Testing
Extensive wind tunnel tests were carried out to determine suitable cross ctional shapes for the deck
and the towers, determine the aerodynamic properties, identify effective wind shields, and confirm the aeroelastic stability of the bridge.  Preliminary ctional tests were carried out at BMT in London.  More extensive tests at larger scales were then undertaken in the 14 m wide by 4 m high wind tunnel at the Politecnico di Milano in Italy.  The included 1 to 30 scale tests of the deck and tower ctions, and a
full aeroelastic model at 1 to 170 scale of the whole bridge in key stages of construction and in the completed state.
Figure 4: Wind Tunnel Testing: deck ction and balanced cantilever from Central Tower
电压力锅排名1484S. KITE et al. / Procedia Engineering 14 (2011) 1480–1484
Author name / Procedia Engineering 00 (2011) 000–000 5
5.CONCLUSIONS
The Forth Replacement Crossing is a major infrastructure project for Scotland, designed to safeguard a vital connection in the country’s transport network. The crossing is located in a historic and
environmentally constrained area, and great consideration has been given to allowing the contractor
sufficient freedom in his design to bring economy, whilst ensuring the final form of the bridge will not
deviate from the client’s expectations. This has been achieved through the production of different
variants of a Specimen Design, with options left open to the contractor for an orthotropic or composite
main deck, and a composite or prestresd concrete approach viaduct.
Figure 5: Night time visualisation
REFERENCES
[1]MACKAY S., “The Forth Bridge – A Picture History”, HMSO, 1993
英雄联盟名字大全[2]ANDERSON J.K., HAMILTON J.A.K., HENDERSON W., STRUTHERS J., ROBERTS G. and SHIRLEY-SMITH H.,
“Forth Road Bridge: History and Finance, Design, Foundations and approach viaducts, Supply and erection of the main
superstructure and Approach roads and administration”, ICE Proceedings, Paper 6890  No. 10, 1965, p. 321-512.
[3]COLFORD B.R., “Forth Road Bridge - maintenance and remedial works”, Proceedings of the Institution of Civil Engineers,
Bridge Engineering No. 161, Sept 2008, p. 125-132.
[4]CARTER M., KITE S., HUSSAIN N., SEYWRIGHT A., GLOVER M., MINTO B., “Forth Replacement Crossing: Scheme
Design of the bridge”, IABSE Symposium Bangkok 2009: Sustainable Infrastructure, IABSE Report Volume 96: p. 382-383.

本文发布于:2023-07-06 19:33:02,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/89/1070623.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:靶心   河套   有关   排名   英雄
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图