1General Provisions一般规定 (9)
1.1Definitions定义 (9)
1.2Interpretation解释 (19)
1.3Communications通信交流 (20)
1.4Law and Language法律和语言 (21)
1.5Priority of Document文件优先次序 (21)
1.6Contract Agreement合同协议书 (22)
1.7Assignment权益转让 (22)
1.8Care and Supply of Document文件的照管和提供 (23)
1.9Confidentiality保密性 (24)
1.10Employer’s U of Contractor’s Documents雇主使用承包商文件 (24)
1.11Contractor’s U of Employer’s Documents承包商使用雇主文件 (25)
1.12Confidential Details保密事项 (26)
1.13Compliance with Laws遵守法律 (26)
1.14Joint and Several Liability共同的和各自的责任 (27)
2The Employer雇主 (29)
2.1Right of Access to the Site现场进入权 (29)
2.2Permits, Licences or Approves许可、执照或批准 (30)
hugged2.3Employer’s personnel雇主人员 (31)慈溪鸣鹤古镇
2.4Employer’s Financial Arrangements雇主的资金安排 (32)
2.5Employer’s Claims雇主的索赔 (32)
3The Employer’s Administration雇主的管理 (35)
3.1The Employer’s Reprentative雇主代表 (35)
3.2The Employer’s personnel其他雇主人员 (36)
3.3Delegated Persons受托人员 (36)
3.4Instructions指示 (37)
3.5Determinations确定 (38)
4The Contractor承包商 (40)
4.1The Contractor’s General Obligations承包商的一般义务 (40)
4.2Performance curity履约担保 (41)
4.3Contractor’s Reprentative承包商代表 (43)
4.4Subcontractors分包商 (45)
4.5Nominated Subcontractors指定的分包商 (46)
4.6Co-operation合作 (46)
4.7Setting out放线 (48)
4.8Safety procedures安全程序 (48)
4.9Quality Assurance质量保证 (49)
4.10Site Data现场数据 (50)
4.11Sufficiency of the Contract Price合同价格 (50)
4.12Unforeeable Difficulties不可预见的困难 (51)
4.13Rights of way and Facilities道路通行权于设施 (52)
4.14Avoidance of Interference避免干扰 (52)
4.15Access Route进场通路 (53)
4.16Transport of Goods货物运输 (54)
4.17Contractor’s Equipment承包商设备 (55)
4.18Protection of the Environment环境保护 (55)
4.19Electricity, Water and Gas电、水和燃气 (55)
4.20Employer’s Equipment and Free-Issue Material雇主设备和免费供应的材
料 (56)
4.21Progress Reports进度报告 (58)
4.22Security of the Site现场保安 (60)
4.23Contractor’s Operations on Site承包商的现场作业 (61)
4.24Fossils化石 (62)
5Design设计 (64)
5.1General Design Obligations设计义务一般要求 (64)
5.2Contractor’s Documents承包商文件 (65)
5.3Contractor’s Undertakin g承包商的承诺 (68)
5.4Technical Standards and Regulations技术标准和法规 (68)
5.5Training培训 (69)
5.6As-Built Documents竣工文件 (70)
5.7Operation and Maintenance Manuals操作和维修手册 (71)
5.8Design Error设计错误 (71)
最大的食肉恐龙
6Staff and Labour员工 (72)
6.1Engagement of Staff and Labour员工的雇用 (72)
6.2Rates of Wages and Conditions of Labour工资标准和劳动条件 (72)
6.3Persons in the Service of Employer为雇主服务的人员 (72)
6.4Labour Laws劳动法 (73)
6.5Working Hours工作时间 (73)
6.6Facilities for Staff and Labour为员工提供设施 (74)
6.7Health and Safety健康和安全 (74)
6.8Contractor’s Superintendence承包商的监督 (75)
6.9Contractor’s Personnel承包商人员 (76)
6.10Records of contractor’s Personnel and Equipment承包商人员和设备的记
录 (77)
6.11Disorderly Conduct无序行为 (77)
7Plant, Materials and Workmanship生产设备、材料和工艺 (79)
7.1Manner of Execution实施方法 (79)
7.2Samples样品 (79)
7.3Inspection检验 (80)
7.4Testing试验 (81)
7.5Rejection拒收 (83)
7.6Remedial Work修补工作 (84)
7.7Ownership of Plant and Materials生产设备和材料的所有权 (85)
7.8Royalties土地(矿区)使用费 (85)
8Commencement,Delays and Suspension开工、延误和暂停 (87)
8.1Commencement of Works工程的开工 (87)
8.2Time for Completion竣工时间 (87)
8.3Programme进度计划 (88)
丹参功效与作用8.4Extension of Time for Completion竣工时间延长 (90)
8.5Delays Caud by Authorities当局造成的延误 (91)
8.6Rate of Progress工程进度 (92)
8.7Delay Damages误期损害赔偿费 (93)
8.8Suspension of Work暂时停工 (94)
8.9Conquences of Suspension暂停的后果 (94)
8.10Payment for Plant and Materials in Event of Suspension暂停时对生产设
备和材料的付款 (95)
8.11Prolonged Suspension托长的暂停 (96)分房协议
8.12Resumption of Work复工 (96)
9Tests on Completion竣工试验 (97)
9.1Contractor’s Obligations承包商的义务 (97)
9.2Delayed Tests延误的试验 (99)
9.3Retesting重新试验 (100)
9.4Failure to Pass Tests on Completion未能通过竣工试验 (100)
10Employer’s Taking Over雇主的接收 (102)
10.1Taking Over of the Works and Sections工程和分项工程的接收 (102)
10.2Taking Over of Parts of the Works部分工程的接收 (103)
10.3Interference with Tests on Completion对竣工试验的干扰 (104)
11Defects Liability缺陷责任 (105)
11.1Completion of Outstanding Work and Remedying Defects完成扫尾工作
和修补缺陷 (105)
11.2Cost of Remedying Defects修补缺陷的费用 (106)
11.3Extension of Defects Notification Period缺陷通知期的延长 (107)
11.4Failure to Remedy Defects未能修补的缺陷 (107)
11.5Removal of Defective Work移出有缺陷的工程 (109)
11.6Further Tests进一步试验 (109)
11.7Right of Access进入权 (110)
11.8Contractor to Search承包商调查 (110)
11.9Performance Certificate履约证书 (111)
11.10Unfulfilled Obligations未履行的义务 (112)
11.11Clearance of Site现场清理 (112)
12Tests after Completion竣工后试验 (114)
12.1Procedure for Tests after Completion竣工后试验的程序 (114)
12.2Delayed Tests延误的试验 (115)
12.3Retesting重新试验 (116)
今日七夕
12.4Failure to Pass Tests after Completion未能通过的竣工后试验 (117)
13Variations and Adjustments变更和调整 (119)
13.1Right to Vary变更权 (119)
13.2Value Engineering价值工程 (119)
13.3Variation Procedure变更程序 (120)
13.4Payment in Applicable Currencies以适用货币支付 (121)
13.5Provisional Sums暂列金额 (122)
13.6Daywork计日工作 (123)
13.7Adjustments for Changes in Legislation因法律改变的调整 (124)
13.8Adjustments for Changes in Cost因成本改变的调整 (126)
14Contract price and Payment合同价格和支付 (127)
14.1The Contract Price合同价格 (127)
14.2Advance payment预付款 (127)
14.3Application for Interim Payments期中付款的申请 (130)
>家常土豆泥

本文发布于:2023-07-05 19:48:59,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/89/1069221.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:承包商   雇主   竣工   设备   文件   缺陷   试验   工程
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图