超平地坪施工方案(英汉双语)

更新时间:2023-05-28 03:45:16 阅读: 评论:0

超平地坪施工方案
超平地坪施工方案  Construction Scheme for Flat Floor
一、施工程序框图与施工步骤
Construction procedure frame and construction scheme
1. 地坪标高确认:
Confirm floor elevation
a.现场确认平整度基准点。
Datum mark must be confirmed on site.
无妨b.检查原地面垫层的标高状况,对严重高低不平处进行处理。
Check subba surface elevation before concrete cast work, and deal with the riously rugged place.
2. 地坪模板确认 
Confirm formwork
水母画Confirm elevation of the formwork.
Confirm stability of the formwork.
3. 混凝土供应及铺筑
Cast Concrete
a.混凝土材料要求:
Concrete requirement:
-        混凝土标号为C30;
Concrete compressive strength: C30;
-        粗骨料最大粒径不超过25mm;
Largest size of  coar aggregate : 25mm;
-        塌落度为10cm±2;
Slump: 10±2 cm;
±1.0% 以内
Air content within 3.0±1.0%;
送你的独白-        同一施工现场应使用同一公司的商品混凝土;
    Concrete must be supplied by the same company on the same construction site;
-        混凝土泵车的运输时间不应超过40分钟,搅拌车之间的时间间距不应超过10分钟;
Transport time of concrete pumping truck should not exceed 40 minutes;
-        塌落度测试标准,每60m³检查对1台泵车进行测试;
Slump test must be carry out every 60m³ concrete;
雅字五行属什么-        其他为注明事宜,根据乙方的配比;
Others undertake according to party B’s concrete mix design.
b. 铺筑前拟定计划,并审核;
Make a scheme and certificate before concrete cast
苹果手机怎么强制开机
-  混凝土铺筑是影响混凝土品质的主要环节,因此必须事先拟定好计划,并得到项目监理的认可;威宁地震
Concrete casting is the most important part through the entire construction process which can influence the quality of concrete directly, so a scheme must be well-prepared in advance and certificate by project monitor.
- 拟定混凝土铺筑计划时需考虑的事宜:
Matters below must be taken into account when a concrete casting scheme is drafted:
* 现场混凝土输送通道及 设备进出的通道。
On site passages for concrete transport and equipments entrance.
营业成本包括哪些*日铺筑面积;
Casting areas per day.
* 混凝土铺筑量;
Casting quantity of concrete.
*运输时间;
Transport time of pumping truck.
* 搅拌车数量;
Numbers of pumping truck.
* 铺筑作业及人员编排;
Casting work and workers arrangement.
* 设定铺筑区域;
Arrange casting district.
* 新老混凝土结合部位的处理;
Joint treatments between the old and new concrete.
* 铺筑人员的结构;
Frame of construction workers.
- 监理人员审核铺筑计划时,应对会影响混凝土铺筑的各个因素及实施的可行性等一一审核;
Every possible factor that could influence concrete casting and construction feasibility must be audit when a monitor is auditing a casting scheme.
- 混凝土铺筑前必须仔细确认每项事宜,如发生未准备事宜而需要延长时间时,必须对已施工区域进行保养,以防止混凝土铺筑前异物混入等。
Everything related must be affirmed carefully before concrete casting. Once something unexpected happened during construction and a prolonged time is needed, curing must be taken immediately to the accomplished area in order to prevent foreign material mix in.
- 混凝土铺注前需确认的事宜:
Matters below must be taken into account before concrete casting:
* 铺筑时水平标准点的设置;
Surveyor’s pole t-up method.
* 表面的清洁;
  Surface cleaness.
* 混凝土铺筑设备确保与否;
  Concrete screeding equipment.
* 混凝土地坪的厚度;
The thickness of RC layer.
c. 混凝土铺筑标准:
    Concrete casting standard:
乳头很痒怎么回事-混凝土铺筑时,从开始到结束自始自终严格进行管理。
Governing strictly all along the construction time.
- 混凝土铺筑方向是以一个方向为原则(从左侧开始,往右侧移动,一排结束后重复进行)。
Concrete casting direction should be one in principle (usually start from the left, and move to the right direction, and repeat it when one strip is finished).
- 夏天铺筑时避免发生施工缝,为了防止发生冷缝,与商混公司协商,避免水泥泵车延迟的情况发生。
In summer, concrete is likely to desiccate. But the quantity of construction joint must be mostly reduced. So it is necessary to consult with the commercial concrete company to avoid retardation caud by pumping truck.
二、激光整平机整平:
Concrete screed with Larscreed
- 激光整平机简介:
Brief introduce of Larscreed

本文发布于:2023-05-28 03:45:16,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/82/796801.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:铺筑   混凝土   施工   计划   事宜
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图