How Large Are Software Cost Overruns?
A Review of the 1994 CHAOS Report
Magne Jørgenn1 and Kjetil Moløkken
Simula Rearch Laboratory
Abstract:The Standish Group reported in 1994 that the average cost overrun of software projects was as high as 189%. This cost overrun number is ud as input in recent governmental reports on software development and as benchmark for veral recent projects’ estimation performances. It is therefore important that we can trust this number. More recent cost overrun results reported by the Standish Group and others, however, show much lower cost overrun. Does this mean that software companies have improved their estimation ability strongly the last 10 years? In this paper we argue that there are reasons to doubt the validity of the Standish Group’s 1994 cost overrun results and that a continued u of the results may hinder progress.
Keywords: Software cost estimation, rearch method, review.
1 Introduction
The Standish Group () claims that the results of their CHAOS rearch, i.e., their large-scaled surveys conducted in 1994, 1996, 1998, 2000 and 2002, are the most widely quoted statistics in the IT industry. This may very well be true. Quoted with particular frequency are the results described in the 1994 CHAOS report [1]. The results of that report have been ud in veral recent governmental reports, project reviews, and rearch studies, e.g., the PITAC 1999 report [2]. An important result from the 1994 CHAOS rearch is the reported 189% average cost overrun of so-called challenged projects, i.e., projects not on time, on cost, and with all specified functionality. The question we try to answer in this paper is whether we can trust the cost overrun numbers, implying a ‘software crisis’, described in the 1994 CHAOS report.
The paper is organized as follows: Section 2 discuss and exemplifies the importance of the correctness of the 1994 cost overrun number reported by the Standish Group, Section 3 compares the CHAOS report results with tho of similar software cost estimation surveys, Section 4 discuss potential reasons for differences in results between the 1994 CHAOS report and similar surveys, Section 5 describes lessons learned from the review of the 1994 CHAOS report, and, Section 6 summarizes the paper.
1 Corresponding author: Magne Jørgenn, Simula Rearch Laboratory, P.O.Box 134, NO-1325 Ly
saker, Norway. Telephone: +47 924 333 55. Fax: +47 67 8
2 82 01. email:
高级职员2The Importance of the Correctness of 189% Average Cost Overrun Result
Among the urs of the cost overrun numbers in the 1994 CHAOS report are scientific rearchers, software process improvement groups, and government advisors. The main u ems to be to argue for more rearch, better estimation process and improved project management methods. The are all laudable goals, well supported by a ‘software cost estimation crisis’ implied by a 189% average cost overrun. Unfortunately, there are veral examples of situations where the 189% result may have hindered progress. The following three real-world examples illustrate this.
Example 1: A project had a 146% cost overrun, i.e., the actual cost was about 2.5 times the estimated cost. A report on the project’s performance stated that the cost overrun was not that bad, becau it was better than the industry average of 189%. There are veral examples of this type of u.
Example 2: A consultancy company claimed to be in the elite class of software development companies, bad on a comparison of its own numbers with the 189% cost overrun number.
Example 3: A recent UK study of software projects [3] report an average cost overrun of 18%. Here an adjusted version of the 189% cost overrun number from the 1994 CHAOS report is ud to support an argument for an enormous improvement in estimation performance. Readers of that report may get the impression that the improvement of cost estimation process does not require a great deal of systematic work and focus.
3  A Comparison with Other Cost Estimation Accuracy
Studies
Before we compare the CHAOS Report results with tho of other studies it is important to clarify the meaning of ‘189% average cost overrun’. This turned out to be more difficult than expected. In fact, we were unable to find an explicit definition of the cost overrun measure applied in the CHAOS reports. Only informal, inconsistent descriptions were prented. The following quotations provide typical examples of how the CHAOS reports describe the 189% average cost overrun:
• “… 52.7%of projects will overrun their initial cost estimates by 189%”, page 41 in [4].
o Comment: 52.7% is identical to the percentage of so-called challenged projects. Even the definition of challenged projects is not easy to interpret.
It is defined in [1] as “The project is completed and operational but over-
budget, over the time estimate, and offers fewer features and functions
than originally specified.” The problem here is the u of “and” instead of
“or”, combined with the following definition of successful projects: “The
project is completed on-time and on-budget, with all features and
functions as initially specified.” Consider a project that is on-time, and on-
budget, but not with all specified functionality. Is this project to be
生活垃圾填埋场categorized as challenged or successful? Our guess is that it would be
categorized as challenged, but this is not consistent with the provided
definition of challenged projects.
•“The average cost overruns for combined challenged and cancelled projects is 189%.”, page 42 in [4].
o Comment: Here, the cancelled projects are included, i.e., there are two inconsistent descriptions of cost overrun in the same document. The
method by which the cost overrun of a cancelled project might be included
is not given.
•“… 52.7% of projects will cost 189% of their original estimates”, page 14 in [5].
o Comment: As we interpret it, if the cost is 189% of an estimate there is an 89% cost overrun, i.e., this is not the same as the first description.
To e whether we were the only ones confud by the descriptions we conducted a simple survey of the actual u of the 1994 CHAOS report cost overrun number. We examined 50 randomly sampled web-documents applying the arch term: ((Standish Group) AND (189% OR 89%)) and the arch engine We found the following:
•50% of the documents described the result as “189% cost overrun”, 40% as “189% of original estimate”, and 10% as “89% cost overrun”. “189% of original estimate” and “89% cost overrun” em to reflect the same understanding of the result, i.e., we found two different interpretations of cost ove
rrun that were ud with almost the same frequency.
•70% of the documents related the result to “53% of the projects” (without explicitly pointing out that this 53% referred to challenged projects only), 16% to “all projects”, 8% to “challenged and cancelled projects”, and 6% explicitly pointed out that the average cost overrun is bad on “challenged projects” only.
Generally, in recent reports and press releas the Standish Group ams to apply the interpretation “189% average cost overrun of challenged projects”, e for example the press relea March 2003 [6]. This means that many, perhaps the majority, of the urs interpret the results differently from the Standish Group.
All surveys of cost estimation accuracy in the relevant period and countries that we were able to find suggest average cost overrun in the range of about 30% (e Table 1), i.e., values far from 189% cost overrun.  The surveys in Table 1 have all been subject to scientific review of rearch method and results, as oppod to the Standish Group CHAOS reports. For a more detailed description of the and other cost estimation surveys, e [7].
Table 1: Cost Overrun Surveys
Study Jenkins [8] Phan [9] Bergeron [10]
Year 1984
1988
1992陆游是哪个朝代的
Respondents
23 software
organizations
191 software
projects
89 software
projects
Country of
Respondents USA USA Canada
Average Cost
Overrun  34%  33% 33%
The values are not directly comparable with tho in the CHAOS reports. The studies in Table 1 include successful as well as challenged projects, as oppod to the CHAOS report where the successful projects are excluded from the cost overrun calculation. However, the proportion of successful projects in the 1994 CHAOS report was only 16% and cannot explain the huge difference in the results. The question is therefore: Are there other differences between the three studies in Table 1 and the CHAOS 1994 survey that can explain the huge difference in average cost overruns? Are there, for example, reasons to believe that the cost accuracy performance was so much wor in 1994 than in the period 1984-1992, or that the three studies in Table 1 are bias towards too low cost overruns? We can find no such reasons explaining the difference in results.
Interestingly, the Standish Group’s CHAOS surveys for the years 1996, 1998, 2000, and 2002 report
strongly decreasing numbers, i.e., 142%, 69%, 45%, and 43% average cost overrun. Adjusted for differences in how cost overrun is measured, we find that the numbers for 2000 and 2002 corresponds well with the average cost overrun of about 30% in the studies in Table 1, i.e., it ems as if it is mainly the early (1994, 1996 and 1998) CHAOS report cost overrun numbers that are unusual. The strong decrea in average cost overrun, as measured by the Standish Group, is a reason to doubt the rearch method in itlf. For example, do we believe that the average cost overrun improved from 142% to 69% in only two years?
4Why Are the Cost Overruns in the 1994 CHAOS Report So High?
To investigate reasons for the high 1994 cost overrun number, we asked the Standish Group how they lected the projects to be included in their CHAOS studies and how we should interpret ‘cost overrun’. The respon to our rearch method question was that providing this type of information would be like giving away their business for free, and we got no respon on how to interpret ‘cost accuracy’. This unwillingness to reveal rearch method and measurement definitions would have been an unacceptable respon in an academic context, but is, as far as we have experienced, not uncommon in commercial companies conducting rearch studies.
This lack of rearch method and measurement definition information leaves us with no choice but to speculate about potential reasons. We have identified the following
potential reasons explaining the ‘189% cost overrun’ reported in the 1994 CHAOS rearch report:
•Incorrect interpretation of own results: Re-calculations of the average cost overrun bad on the Standish Groups 1994 distribution of cost overrun per overrun category results in a cost overrun clo to 89%, i.e., there may be an inconsistency between the two prentations (average cost overrun and cost overrun distribution) of the overrun data. When the Standish Group prent the 1994-study as 189% instead of 89% cost overrun, it may have been misled by its own confusing description of the results. However, even a reduction from 189% to 89% does not lead to results on the level of the comparable studies.
•No category for cost under-run: In most studies on software cost accuracy there is
a proportion of projects with cost under-runs. For example, in the recent UK study
on project performance [3] as many as 15% of the projects were completed ahead of budget. Even challenged projects may have cost under-runs, since they may be challenged only regarding time or
天真岁月不忍欺
functionality. We find no reference to or description of treatments of cost under-run in the Standish Group’s reports. It is therefore possible that cost under-runs are not included as cost under-runs, but perhaps as 0% cost overrun.
•Unusual definition of cost overrun: The Standish Group may have ud an unusual definition of cost overrun, e.g., the definition may include cost on cancelled projects as indicated in one of the three informal descriptions of cost overrun.
韩国萝卜泡菜
•Non-random sampling of projects. Unusual results are sometimes caud by non-random samples. A thorough reading of the version 3.0 of the CHAOS report provides some support for this explanation. On page 13 the lection process of the 1994-study is described as follows: “We then called and mailed a number of confidential surveys to a random sample of top IT executives, asking them to share failure stories [!!!]. During September and October of that year, we collected the majority of the 365 surveys we needed to publish the CHAOS rearch.” The decreasing average cost overrun numbers of more recent CHAOS rearch may therefore be a conquence of an increasingly more reprentative (and less failure-story related) lection of projects.
5What Should We Learn From This?
This paper does not prove that the 189% average cost accuracy reported in the 1994 CHAOS report is biad and unreprentative for the situation in 1994. Such a proof would require the availability of information that the Standish Group will not relea. It is possible that the results are valid, and merely very difficult to interpret, given the lack of measurement definitions and rearch study description. Bearing in mind the above cautionary note as to what we are able to establish, we have attempted to provide reasons to doubt the 189% average cost overrun value as it is interpreted by most of its urs. In particular we believe that the unusually high average cost accuracy number and the lack of rearch method description are valid reasons for doubting that number. As software cost estimation rearchers, we (the authors of this paper) and many others have
uncritically applied the 1994 CHAOS Report cost overrun numbers to veral studies, e.g., in [11, 12]. We believe therefore that there are lessons to be learned:
Lesson 1: When something does not correspond with own experience and other studies, doubt it. An 189% average cost overrun, as reported by the CHAOS rearch, is an extremely high number in relation to numbers reported in other studies. Conquently, we should require a detailed description of rearch method applied or independent studies that replicate the result before believing it.
五言律诗的特点
Lesson 2: The number of obrvations, which is higher in the CHAOS report than in the comparable studies, is not always a good indicator of the validity of the results. We should be just as concerned about the lection process as with the number of obrvations. If the lection process is not properly described, we should doubt the results regardless of the number of obrvations. Bias is not removed with an incread number of obrvations.
Lesson 3: Studies that do not precily define their measures, as is the ca with the CHAOS rearch, should be interpreted carefully. The confusion about the interpretation of the 189% average cost overrun illustrates this. For example, many documents referring to the CHAOS report did not notice that the average cost accuracy only referred to challenged (and maybe cancelled) projects, not to all projects.
6 Summary
The Standish Group reported in 1994 that the average cost overrun of software projects was as high as 189%. This cost overrun number is still of great importance. It is, for example, ud as input in recent governmental reports, as benchmark for the estimation performance of recent projects, and to support the claim that there has been an immen improvement in cost estimation performance the l
屁股美女ast 10 years. We found veral reasons to believe that an average cost overrun of 189% is much too high to reflect the situation in 1994. The number not consistent with cost overrun results of other surveys in that period, and, there may be rious problems with how the Standish Group conducted their rearch. Unfortunately, the Standish Group provides an incomplete description of how they conducted their studies, e.g., how they lected the projects to be included in the study, and does not include a description of how the measure ‘cost overrun’. This makes it difficult to evaluate the validity of their 1994 study. Even wor, the lack of preci definition of ‘cost overrun’ ems to have created much confusion. Many, perhaps the majority, of the urs interpret the cost overrun results differently from the Standish Group. Our main conclusion is that we should doubt the validity of the 189% average cost overrun reported by the Standish Group in 1994 until such time as the Standish Group disclo how they measure cost overrun and how they conduct their rearch. Currently, the validity and comprehensibility of that number is highly questionable and may create the impression (a) that the IT-industry has improved strongly since 1994 and (b) that even very inaccurate projects are “better than average”.

本文发布于:2023-07-19 23:05:04,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/82/1105883.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:生活   韩国   陆游
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图