收藏!船舶装卸时间事实记录参考用语(中英对照)

更新时间:2023-06-05 06:03:33 阅读: 评论:0

收藏!船舶装卸时间事实记录参考⽤语(中英对照)⼀、船舶抵达
1. 抵达引⽔锚地Anchored at Pilot anchorage / Arrived at Pilot anchorage
2. 抵达检疫锚地Anchored at Quarantine anchorage / Arrived at the quarantine anchorage
3. 等候引⽔/等候引航员Awaiting pilot, Waiting for pilot
4. 等候办理进⼝⼿续Waiting for entry (inward) formalities
5. 等候检疫Awaiting quarantine inspection
英语口语8000句 mp3
6. 等候联检Awaiting Joint Inspection
7. 检疫通过Free Pratique granted
8. 进⾏联检Joint Inspection conducted
9. 联检完毕Joint Inspection completed
10. 等候潮⽔进港Awaiting tide for entry
11. 等⾼潮进港Awaiting high tide for entry
12. (从引⽔站)驻往装、卸泊位Proceeding to berth for loading/discharging
13. 从锚驶往装/卸泊位Heaved up (Weighed) anchor and proceeded to berth for loading/discharging
14. 驶靠第X号码头Proceeded & berthed alongside wharf NO…
15. 从浮筒移⾄装/卸泊位Shifting from buoys to loading/discharging berth
16. 船系XX号浮筒Moored at buoys NO…
caucus17. 因…不能进港Failed to enter due to…
18. 因…返回锚地Turned back to anchorage due to…
⼆、装卸准备
1. 等候泊位Waiting for berth
2. 准备装卸Preparation for loading/discharging
3. ⾸末次开盖舱First opening& final closing of hatches
4. 整理吊杆Rigging derricks.
5. 清扫舱(船员/⼯⼈清扫)Cleaning holds (by crew members/shore labors)
6. 铺垫舱Dunnaging and matting
7. ⽔密检验通过Water tight test pasd
8. 接油管Connecting oil pipes
9. 拆油管Disconnecting pipes
10. 搭⾬蓬Erecting rain tentsaeroplane
11. 拆⾬蓬Taking off rain tents
12. 搭防动设备Erecting grain fitting (at hatch NO…)
小学英语故事13. 搭防动板Erecting shifting boards(at hatch No…)
14. 拆防动板Dismantling shifting boards(at Hatch No…)
15. ⼯⼈上船做准备Stevedore boarded for preparation of holds
16. 商检⼈员上船验舱Cargo Surveyors boarded for inspection of holds
17. 商检⼈员验舱Inspecting cargo holds by cargo surveyors
18. 验检不合格Inspection of holds not pasd
19. 等候装卸Waiting for loading/discharging
20. 第X舱商检合格Hold No. X inspection pasd
21. 全部货舱通过All holds inspection pasd
22. 安放漏⽃Erecting feeders
三、装卸作业
1. 开始装卸Loading/discharging commenced
继续装卸Loading/discharging continued
2. 恢复装卸Loading/discharging resumed
3. 暂停装卸Loading/discharging suspended
4. 在⾬蓬下装卸Loading/discharging under rain tents
5. 开⼏条路(⼏个头)装卸Loading/discharging with…gangs
6. 装卸完毕Loading/discharging completed
7. 公估Determine the quantity of cargo loaded/on board by draft survey
8. 卸地脚Discharging cargo sweepings
9. (特殊)平舱(Special) Trimming of cargo
9. (特殊)平舱(Special) Trimming of cargo
10. 扫舱Sweeping holds
11. 等驳船(车⽪) Awaiting lighters/wagons
12. 等加载Awaiting arrangement for additional cargo
13. 等待租⽅装货安排Awaiting Charters’ loading arrangement
14. 等待租⽅装货安排Awaiting shifting
15. 等候舱⼝照明Awaiting cargo lights
16. 因XX原因装/卸暂停No work (Loading/discharging suspended) due to…
17. 读⽔尺公估Determining cargo quantity on board by draft surveyor
四、装卸时间
1. 递交NOR Notice of Readiness tendered
2. 接受NOR Notice of Readiness accepted
3. 收到NOR Notice of Readiness received
4. 开始计算时间Time commenced received
5. ⽤于装/卸的时间Time ud for loading/discharging
6. 不计时间Time not to count
7. 按租约不计时间Time not to count
8. 扣除1/5时间Time deducted by 1/5
9. 星期⽇不计时间Time not count on Sunday
10. 星期六下午不计时间Saturday afternoon, time not to count
11. 例假⽇前⼀天XX时不计时间The day before holiday, time not to count after…hours
12. 例假后⼀天8⼩时前不计时间The day after holiday, time not to count before 8 am
13. 星期⼀8时起前不计时间Monday, time not to count before 8 am
14. 星期⼀从8时起算时间Monday, time to count from 8 am
15. 冷却吸扬机时间Time for cooling the motor of sucker
16. 装卸重货时间Time not to count for loading/discharging heavy lifts
17. ⾬蓬下装卸不计时间Loading/discharging under rain tents, time not to countreply什么意思
18. ⾬蓬下装卸,时间按50%计算Loading/discharging under rain tents, time 50% to count
18. ⾬蓬下装卸,时间按50%计算Loading/discharging under rain tents, time 50% to count
五、因⽓象、船舶属具原因停⼯
1. 因⾬停⼯Loading/Discharging suspended due to the rain
2. 因间断下⾬停⼯Loading/discharging suspended/stopped due to intermittent rain
3. 因防下⾬停⼯Loading/discharging suspended due/owing to precaution against rain
4. 因雷/阵⾬停⼯: Loading/Discharging stopped due to thundering/shower
5. 因天快下⾬Loading/discharging suspended due to threatening weather
6. 因浓雾停⼯Loading/discharging suspended due to den fog
7. 因雪停⼯Loading/discharging suspended due to snow
8. 因⼤风、台风停⼯Loading/discharging suspended due to strong wind/typhoon
9. 因台风警报停⼯: Loading/Discharging stopped due to the typhoon alarm
10. 因⼤浪/巨涌停⼯: Loading/Discharging suspended due to heavy surf/swell
11. 因⽓候不良停⼯Loading/discharging suspended due to bad weather
12. 因潮⽔上码头停⼯Loading/discharging suspended due to tide flooding over the wharf
13. 因台风信号升挂停⼯Loading/discharging suspended due to hoisting of typhoon warning signal
14. 因港⼝受台风影响⽽停⼯Loading/discharging suspended due to the port affected by typhoon
copd是什么意思
15. 台风警报解除Typhoon Alarm relead
16. 因扫沟⽔停⼯Loading/discharging suspended due to sweeping of the bilge
17. 因扫雪停⼯Loading/Discharging suspended due to sweeping snow
18. 移⾄…避风Shifting to…for taking shelter against typhoon/storm
19. 因调整船舶吃⽔停⼯Loading/Discharging suspended owing to adjusting ship’s draft
20. 因修改积载图停⼯Loading/Discharging suspended due to revising stowage plan
21. 等⽕车车⽪Waiting for railway wagons
superheroes22. 等驳船Awaiting barge/lighter
23. 等租家指⽰Waiting for instruction from charterers
24. X舱因绞车故障停⼯Loading/discharging suspended in hatch NO…Due to winch breakdown (trouble)
25. X舱因吊货钢丝故障停⼯Loading/discharging suspended in Hatch NO…Due to cargo runner trouble.
26. X舱因硬尾绳故障停⼯Loading/discharging suspended in hatch NO…Due to winch breakdown (tr隐晦是什么意思
ouble)
27. X舱因货灯故障停⼯Loading/discharging Suspended in hatch NO…Due to failure of cargo light
28. X舱更换滑轮停⼯Loading/discharging suspended in hatch No…owing to replacing of block
29. X舱因更换钢丝绳停⼯Loading/discharging suspended in hatch NO…owing to replacing of cargo runner
30. 因蒸汽不⾜停⼯Loading/discharging suspended due to insufficient Steam
31. 因船舶停电停⼯Loading/discharging suspended due to suspension of ship’s power supply
32. 因灯光不⾜停⼯Loading/discharging suspended due to insufficient light
33. 因主机(辅机)故障停⼯Loading/discharging suspended due to warping the ship forward/astern
34. 因油泵故障停⼯Loading/discharging suspended due to main engine(auxiliary engine)trouble
35. 因船往前(后)绞泊停⼯Loading/discharging suspended due to warping the ship forward astern
36. 因调整前后吃⽔停⼯Loading/discharging suspended due to adjusting draftsticketed
37. 因修改积载图停⼯Loading/discharging suspended due to revising Stowage Planblasphemy
38. 因坏天⽓停⼯Loading/Discharging suspended owing to the bad weather
六、船舶动态
1. 由于低潮往外拉Ship being kept off from due to low water
2. 船舶回靠码头(指重新靠码头)Ship hard up against wharf
3. 移泊Shifting from…wharf (buoys)to…wharf (buoys) / Shifting berth
4. 前后通挡若⼲尺(沿码头前后移动)Warping forward/astern…ft alongside the wharf
5. 起锚并驶往XX泊位: Heaved (Weighed) up anchor and proceeding to berth No. xx
6. 因错过潮⽔⽽未能进港: Failed to enter due to missing high tide
7. 靠往XX泊位: Berthing alongside to berth No. xx
8. 靠妥XX泊位: Berthed alongside to berth No. xx
9. 靠妥且缆绳全部系紧: Berthed alongside and all (lines) fastened
10. 驶往并系泊于XX号浮筒: Proceeding and mooring to buoy No. xx
11. 准备移泊: Preparation for shifting berth
12. 等候移泊: Waiting for shifting berth
13. 移⾄锚地避台: Shifting to the anchorage for taking shelter against typhoon

本文发布于:2023-06-05 06:03:33,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/78/868857.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:时间   装卸   船舶   等候
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图