线性回归与神经网络组合模型实现变形预测

更新时间:2023-05-09 01:39:35 阅读: 评论:0

中国港湾建设
Deformation prediction bad on combination of linear regression and
neural network
XIA Xian-wen 1,CHU Cheng-feng 2,GUO Ji-ming 2
(1.CCCC Third Harbor Engineering Co.,Ltd.,Shanghai 200032,China;
2.School of Geodesy and Geomatics,Wuhan University,Wuhan,Hubei 430079,China )
Abstract :The accuracy of deformation prediction of traditional deformation monitoring single deformation analysis model for the monitoring data of complex construction condition is not high,and it cannot sufficiently meet the requirements of engineering construction deformation prediction.In this paper,a combination forecasting model of linear regression analysis model and nonlinear BP neural network model was studied and established,and it was applied to the deformation monitoring data analyzing for the cofferdam of Taihu tunnel.The results of using traditional weighting and IOWGA operator to establish the combined forecasting model were given.Their forecasting precision was calculated and compared.The results show that the combination model of IOWGA had a better precisio
n than single model.It was also over the traditional weighting combination
model.
Key words :deformation prediction;combination forecasting model;weighting method;IOWGA;forecasting precision 摘
要:传统变形监测单一的变形分析模型,对于复杂施工状况的监测数据,变形预测精度不高,不能充分满足工
程施工变形预测的要求。文中研究建立了一种线性回归分析模型和非线性的BP 神经网络模型相结合的组合预测模型,并将其应用于太湖隧道围堰变形监测数据分析,计算给出了采用经典权和IOWGA 算子两种不同的定权方式建立组合预测模型的效果,对预测精度进行了计算比较。结果表明,采用IOWGA 算子建立组合模型的预测精度优于单一模型的预测精度,也优于经典权的组合模型的预测精度。
关键词:变形监测;组合预测模型;定权方法;IOWGA ;预测精度中图分类号:U655.54;TU433文献标志码:A
文章编号:2095-7874(2021)03-0016-05
doi :10.7640/zggwjs202103004
线性回归与神经网络组合模型实现变形预测
夏显文1,褚成凤2,郭际明2
(1.中交第三航务工程局有限公司,上海
200032;2.武汉大学测绘学院,湖北
武汉
430079)
第41卷第3期2021年3月
Vol.41
No.3
Mar.2021
收稿日期:2020-10-09
修回日期:2021-01-28
作者简介:夏显文(1967—),男,江苏南京人,教授级高级工程师,首席测量工程师,工程测量专业。E-mail :****************
0引言
变形监测是利用各种测量技术获得观测数据,经过数据处理和建模分析得到变形量及变形趋势,为工程施工和运营提供重要的安全信息。变形监测数据建模的单一模型方法主要有回归分析[1]、时间序列[2]、卡尔曼滤波[3]、灰色模型[4]、人工神经网络[5]等,但由于实际施工工程较为复杂,变形监测数据受多种因素影响,单一的变形分析模型不能全面概括数据序列的所有特征,其预测精度不高,
因而近十几年,组合预测模型成为研究热点。
对于组合预测模型而言,子模型的选择和定权方式的选择均能对组合预测的精度产生极大影响。关于子模型的选择,已有研究有:小波分析和灰色模型组合[6]、线性回归和灰色模型组合[7]、灰色模型和BP 神经网络模型组合[8]、小波分析和时间序列模型组合[9]、灰色模型和时间序列模型组合[10]、时间序列模型和BP 神经网络模型组合[11]等。关于定权方式的选择有:熵权法[12]、最优权
2021年第3期
法[13]、IOWGA 算子[14]等。本文针对太湖隧道围堰的变形监测数据进行研究,考虑到监测点中既有随时间线性变化分量,又有非线性变化分量,上述已有组合模型不能很好地反映这种数据特点,因而本文采用一元线性回归和BP 神经网络两种子模型,同时把线性和非线性分量进行考虑,分别采用经典权和IOWGA 算子定权两种方式构建了组合预测模型,对太湖隧道围堰进行变形预测精度分析。
1组合预测模型
1.1变形监测模型选择方法
常用的变形监测模型有回归分析、灰色模型、时间序列、BP 神经网络等。其中,回归分析是线性变形监测模型,而BP 神经网络是非线性变形监测方法,两者相互补充,因此本文选择这两种变形监测模型作为组合预测模型的子模型。
1)一元线性回归
监测点随时间线性变化的趋势,可采用一元线性回归模型来表达[15]。x t =a 0+a 1t +εt (1)式中:x t 为监测点在时间t 的观测值;a 0和a 1为模型参数;εt 为预测误差。
2)BP 神经网络
BP 神经网络由输入层、隐含层、输出层构成,其中隐含层可有多层,同一层神经元之间不存在连接关系,只有层与层之间相互连接。BP 神经网络模型图见图1。
具体过程为:第一步为正向传播过程:输入
向量,根据初始随机设置的各神经元的权系数将向量先向前传播到隐含层,经过激活函数,再根据随机设置的权比把隐含节点的输入信息传播到输出节点,最后输出结果。第二步为反向传播过程:将输出的结果与目标结果进行对比分析并设
置一个阈值,若输出结果与目标结果的差异超出该阈值范围,则进行反向传播,即将在初始权分配的基础上重新调整各层神经元之间的权重分配。然后再进行正向传播,对比分析该次正向传播过程输出的结果与实测结果之间的差异,若在阈值之内,则直接输出,否则重复上述过程[16]。1.2定权方法
组合预测模型的关键在于各个单一变形监测模型的定权方式,选择合适的定权准则,可以有效地提高模型拟合、预测精度。
1)经典权
最常用的经典权定权准则是误差平方和倒数法,即取各个模型的拟合预测值数据序列和实际观测序列的残差序列的平方和的倒数[17]。一般残差数据序列的平方和越大,说明该变形监测模型的拟合值与原始观测数据差异性越大,即该变形监测模型的预测精度越低,将其作为子模型参与组合模型,应对其赋予较小的权系数,故取其倒数。该方法的数学模型如下:
p i
=1/E ii
m
j =1
(1/E jj
)(2)
则有:m
i =1
∑p i =1,p i ≥0。式中:E ii 为第i 种单一预
测模型预测误差平方和;m 为选取进行组合的模型的个数,且满足:E ii =
n
t =1
∑e it
2
=n
t =1
(x t
-x it )2
(3)
式中:x t 为时间t 的实际观测值;x it 和e it 分别为第
i 种单一模型在时间t 的模型拟合值和拟合残差;n 为选取的计算观测值残差的个数。
2)IOWGA 算子
IOWGA 算子的定义如下:
假设存在m 个二维数组
([d 1,b 1],[d 2,b 2],…,[d m ,b m ]),若有:IOWGA P ([d 1,
b 1],[d 2,b 2],…,[d m ,b m ])=m
i =1
∏b
d-index (i )
p i
(4)
则称IOWGA P 是由诱导值序列d 1,d 2,…,d m 所
产生的维诱导有序加权几何平均算子
(Induced Ordered Weighted Geometric Averaging Operator ),简称IOWGA 算子。其中,p i 是与算子相关的权系数,且满足:
图1
BP 神经网络模型图
Fig.1
BP neural network model diagram
(导师信号
)输入层输出层
第一隐层第二隐层夏显文,等:线性回归与神经网络组合模型实现变形预测
17··
中国港湾建设2021年第3期
m
i =1
∑p i
=1,p i
≥0,i =1,2,
,m (5)
d i 是b i 的诱导值,将诱导值序列按照从大到
小的顺序进行排列,则d -index (i )是从大到小排列的诱导值序列的第i 个大的诱导值的下标。IOWGA 算子是对从大到小顺序排列诱导值序列所对应的排序后的实测数据序列进行有序加权几何平均,p i 与b i 的大小以及在原始数据序列中的位置无关,只与其诱导值d i 在原始诱导值序列中的位置有关[18]。
IOWGA 算子的建立流程如下:d it =0,当|x t -x it x t
|≥1时
1-|x t -x it x t |,当0≤|x t -x it x t
|<1时
⎧⎩
⏐⏐⏐⏐⏐⏐⎨⏐⏐⏐⏐⏐⏐(6)
式中:x t 为实际观测值数据序列;x it 为第i 种单一变形监测模型在第t 时刻的模型拟合值;d it 表示第i 个单一变形监测模型在第t 时刻的拟合精度,且d it ∈[0,1]。把各单一变形监测模型的拟合精度d it 作为拟合值的诱导值。于是,m 种单一变形监测模型第t 时刻的拟合精度d it 和该时刻所对应的拟合值x it 就构成了m 个二维数组[d it ,x it ],i =1,2,…,m 。
按照从大到小的顺序对诱导值序列d 1t ,d 2t ,…,d mt 进行排序,设第i 个大的诱导值的下标为d -index (it ),则由拟合精度序列d 1t ,d 2t ,…,d mt 作为诱导值建立的第t 时刻的IOWGA 组合模型拟合值为:
IOWGA P ([d 1t ,
x 1t ],[d 2t ,x 2t ],…,[d mt ,x mt ])=m
i =1
∏x
d-index (it )
p i
,i =1,2,…,m ;t =1,2,…,n (7)
设矩阵P =(p 1,p 2,…,p m )T
为基于IOWGA 算子的组合预测模型中的权系数向量矩阵,在式(7)和残差的平方和最小的约束条件下,利用MATLAB 中的最优化工具箱即可求解权因子的具体数值[9]。
根据预测的连续性原则,在求解得到建模数据的IOWGA 组合预测模型的权系数后就可以进行预测。
1.3
效果评价方法
随着组合预测模型的发展,越来越多的定权方式被提出,为了评价其模型拟合及预测的效果,目前常用的精度评价指标[19]有:
1)平均绝对误差MAE =1
n
n
t =1
∑|x t
-x
^t
|(8)
2)中误差
σ=1n n
t =1
∑(x t -x ^t )2
(9)2应用实例分析
太湖隧道是一条高速公路隧道,位于常州至无锡之间。该隧道于2018年1月开始施工,预计2021年底完成,建成后或将成为全国最长的水下高速公路隧道。太湖隧道采用明挖法施工,首先需要建立围堰。施工过程中由于工况变化,可能发生围堰变形,需要对围堰的变形情况进行监测。采用测量机器人观测和三维激光扫描两种技术进行了围堰变形监测,监测得到的观测值为工程坐标系下的(X ,Y )坐标值。本文采用位于围堰上的2-6-099号点从2020-01-18—2020-04-06期间的
58期观测成果进行研究分析。2-6-099号点在围堰上的相对位置如图2所示。
垂直于围堰的变形是监测工作最重要的信息,因此将(X ,Y )转换为在平行于围堰(X′)和垂直于围堰(Y′)这两个方向为坐标轴的坐标值,后续进一步对Y′进行研究分析。转换公式为式(10),几何关系见图3所示。
X′=X A 2+Y A 2√sin (π/2-α-β)
Y′=X A 2
+Y A 2
√cos (π/2-α-β){
(10)
其中,tan β=Y A /X A 。
图2
监测点的相对位置图
Fig.2
The relative position graph of the monitoring points
2-6-094
18··
2021年第3期
2-6-099号点从2020-01-18—2020-04-06期
间的67期观测成果的Y′坐标序列如图4所示
(为了清楚地展现,本文采用的数据统一减去监测点
坐标的整数值)。由于太湖隧道仍在施工建设,施工工况随时间不断变化,监测点的位移变化与工况密切关联,因而本文只对其做1期预测,即利用前67期观测数据预测第68期,前68期观测预测第69期,以此类推。但单次1期预测也存在随机性,因此本文共做了12组1期预测,利用12组预测值和实际
观测值求差得出其中误差,利用中误差进行效果评价。分别建立回归分析和BP 神经网络两种单一变形监测模型,以及对这两种变形监测模型分别采用经典权、IOWGA 算子定权这两种定权方式建立组合预测模型,预测结果如表1所示。
图3坐标轴旋转示意图
Fig.3
Diagram of rotation of axes
图4点2-6-099的开始67期Y ′坐标及第68—79期的1期预测值
Fig.4The starting 67term Y ′of point 2-6-099and the 1step forecasting value for 68-79term
预测期实测数据线性回归BP 神经网络经典权IOWGA 算子680.41300.41190.40960.41050.4096690.41220.41240.41000.41080.4124700.41160.41280.40990.41100.4128710.41050.41310.41030.41160.4131720.40940.41380.41190.41280.4119730.40920.41400.40860.41100.4086740.40890.41410.40990.41160.4099750.40860.41420.40950.41120.4095760.41700.41430.41050.41220.4105770.41660.41480.41080.41210.4148780.42040.41530.41680.41620.416879
0.4210
0.4160
0.4185
0.4175
0.4185
表1
12组1期预测的实测值和模型值对比
Table 1Comparison of the measured values and model
values for 1step forecasting of 12groups
m
表2
各模型预测精度评价
Table 2
Evaluation of prediction accuracy of each mode
参数线性回归BP 神经网络经典权IOWGA 算子
中误差/mm
3.78
3.20
3.05
2.78
0.430.420.410.400.390.380.370.36
时间/d
夏显文,等:线性回归与神经网络组合模型实现变形预测
根据4种方式的12组预测值,计算得到相应的中误差,结果如表2所示,从表2中可以看出:
组合预测模型的预测精度优于单一变形监测模型,IOWGA 算子的组合预测模型的精度又优于经典权模型。
3结语
本文利用一元线性回归模型和非线性的BP 神经网络模型作为子模型,分别采用经典权和IOWGA 算子定权法建立了组合模型,基于对太湖隧道围堰的观测数据进行预测精度分析,结果表明,组合预测模型的预测精度优于单一变形监测模型,组合预测模型中,IOWGA 算子定权组合模型的预测精度优于经典定权组合模型的预测精度。
一元线性回归和非线性的BP 神经网络模型按IOWGA 算子定权的组合模型对既有线性变形又有
19··
中国港湾建设2021年第3期
非线性变形的监测数据序列具有较好的描述,用于太湖隧道施工围堰的变形预测比已有方法取得了更好的效果。
参考文献:
[1]EZEKIEL Mordecai.The assumptions implied in the multiple regression equation[J].Journal of the American Statistical Associa-tion,1925,20(151):405-408.
[2]PERSONS WARREN M.Correlation of time ries[J].Journal of the American Statistical Association,1923,18(142):713-726. [3]金廷文.卡尔曼滤波在变形监测中的应用[J].中国港湾建设,2015,35(7):11-13.
JIN Ting-wen.Application of Kalman filter in deformation monitor-ing[J].China Harbour Engineering,2015,35(7):11-13. [4]陈璐,马惠彪.基于灰色组合预测的沿海围垦区基坑工程深层
土体变形研究与控制[J].中国港湾建设,2019,39(11):1-5,21. CHEN Lu,MA Hui-biao.Study and control of deep soil deforma-tion of foundation pit engineering in coastal reclamation area bad on grey combination prediction[J].China Harbour Engineering, 2019,39(11):1-5,21.
[5]马丽霞,逄超,陈晓辉.BP神经网络的改进算法及在大坝变形
分析与预报中的应用[J].吉林建筑大学学报,2016,33(4):31-34.
MA Li-xia,PANG Chao,CHEN Xiao-hui.Modified algorithm of BP neural network and its application on analysis and prediction of dam deformation[J].Journal of Jilin Jianzhu University,2016,33 (4):31-34.
[6]徐秀杰,黄张裕,凌晨阳,等.基于小波分析的灰色组合模型在
变形监测数据处理中的应用[J].工程勘察,2014,42(4):80-83. XU Xiu-jie,HUANG Zhang-yu,LING Chen-yang,et al.Applica-tion of grey theory and wavelet in deformation monitoring data pro-cessing[J].Geotechnical Investigation&Surveying,2014,42(4): 80-83.
[7]郭锴,陈伟清,文鸿雁,等.非等时距灰色线性组合模型在变形
监测中的应用[J].测绘科学,2014,39(7):131-135. GUO Kai,CHEN Wei-qing,WEN Hong-yan,et al.A comparative study of non-equal interval gray linear combination model in deformation monitoring[J].Science of Surveying and Mapping, 2014,39(7):131-135.
[8]李进,黄张裕,欧阳经富,等.灰色神经网络组合模型在变形监
测数据分析中的应用[J].勘察科学技术,2016(5):48-50.
LI Jin,HUANG Zhang-yu,OUYANG Jing-fu,et al.Application of grey neural network combined model in deformation monitoring data analysis[J].Site Investigation Science and Technology,2016 (5):48-50.
[9]刘江,苗昌奇,陈柳阳.小波-时序组合模型在地铁变形监测预
测中的应用研究[J].测绘与空间地理信息,2018,41(11):254-256.
LIU Jiang,MIAO Chang-qi,CHEN Liu-yang.Application of wavelet-timing combination model to prediction of metro deforma-tion monitoring[J].Geomatics&Spatial Information Technology,
2018,41(11):254-256.
[10]张正虎,袁孟科,邓建辉,等.基于改进灰色-时序分析时变模
型的边坡位移预测[J].岩石力学与工程学报,2014,33(S2):3791-3797.
ZHANG Zheng-hu,YUAN Meng-ke,DENG Jian-hui,et al.Dis-placement prediction of slope bad on improved grey-time ries time-varying model[J].Chine Journal of Rock Mechanics and Engineering,2014,33(S2):3791-3797.
[11]王磊,高峰.基于时间序列-BP神经网络在基坑方面的应用研
究[J].测绘与空间地理信息,2018,41(6):201-205. WANG Lei,GAO Feng.Application rearch of foundation pit bad on time ries and BP neural network[J].Geomatics&Spatial Information Technology,2018,41(6):201-205.
[12]郑旭东,陈天伟,邓捷利,等.熵权法并联组合模型在大坝变形
监测中的应用[J].水力发电,2019,45(3):115-119. ZHENG Xu-dong,CHEN Tian-wei,DENG Jie-li,et al.Applica-tion of parallel combination model of entropy eight method in dam deformation monitoring[J].Water Power,2019,45(3):115-119.
[13]张吉艳,蔡德所,郭雅男,等.最优加权组合预测模型在大坝变
形监测中的应用[J].人民珠江,2016,37(10):100-104. ZHANG Ji-yan,CAI De-suo,GUO Ya-nan,et al.Application of combination forecast model to the dam deformation monitoring data [J].Pearl River,2016,37(10):100-104.
[14]赵鑫,杨德宏,秦国玲,等.一种基于IOWGA算子的沉降组合
预测方法及其应用[J].工程勘察,2015,43(8):87-92. ZHAO Xin,YANG De-hong,QIN Guo-ling,et al.A combination ttlement forecasting method bad on IOWGA operator and its application[J].Ge
otechnical Investigation&Surveying,2015,43 (8):87-92.
[15]黄声享,尹晖,蒋征.变形监测数据处理[M].武汉:武汉大学出
版社,2010.
HUANG Sheng-xiang,YIN Hui,JIANG Zheng.Deformation moni-toring data processing[M].Wuhan:Wuhan University Press,2010.
[16]傅湘萍.地铁结构变形预测组合模型构建及应用研究[D].南
京:东南大学,2017.
FU Xiang-ping.Rearch of subway structure deformation bad on combined model[D].Nanjing:Southeast University,2017. [17]杜琨.变形监测数据处理的方法研究[D].长沙:中南大学,2013. DU Kun.Rearch on data processing method of deformation moni-toring[D].Changsha:Central South University,2013. [18]杨建文.变形预测组合模型建模方法研究与精度分析[D].昆
明:昆明理工大学,2014.
YANG Jian-wen.Study on modeling method and precision analysis of deformation prediction combination mode[D].Kunming:Kunming University of Science and Technology,2014.
[19]牟洪洲.建筑沉降监测数据处理组合模型研究[D].西安:长安
大学,2008.
MOU Hong-zhou.Study on the combination models in data pro-cessing of deformation monitoring[D].Xi'an:Chang'an University, 2008.
20··

本文发布于:2023-05-09 01:39:35,感谢您对本站的认可!

本文链接:https://www.wtabcd.cn/fanwen/fan/78/560703.html

版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。

标签:模型   预测   变形   组合   监测   序列
相关文章
留言与评论(共有 0 条评论)
   
验证码:
推荐文章
排行榜
Copyright ©2019-2022 Comsenz Inc.Powered by © 专利检索| 网站地图